April 14, 2021 - Minutes


PDF Document Printer-Friendly Minutes

City of Richmond Meeting Minutes

 

 

 Development Permit Panel

Wednesday, April 14, 2021

Time:

3:30 p.m.

Place:

Remote (Zoom) Meeting

Present:

Joe Erceg, Chair 
Cecilia Achiam, General Manager, Community Safety 
Milton Chan, Director, Engineering


The meeting was called to order at 3:30 p.m.

 

Minutes

 

It was moved and seconded

 

That the minutes of the meeting of the Development Permit Panel held on March 24, 2021 be adopted.

 

CARRIED


1.

DEVELOPMENT PERMIT 17-792931   
(REDMS No. 6612976)

 

APPLICANT:

Urban Era Builders & Developers Ltd.

 

 

PROPERTY LOCATION:

9700, 9720 and 9800 Williams Road

 


 

INTENT OF PERMIT:

 

Permit the construction of 18 townhouses, including three affordable housing units, at 9700, 9720 and 9800 Williams Road on a site zoned “Town Housing (ZT81) - Williams Road”.


 

Applicant’s Comments

 

Khalid Hasan, Urban Era Builders and Developers, Ltd., introduced the project, noting that the project includes three affordable housing rental units.

 

Eric Law, Eric Law Architect, with the aid of a visual presentation (copy on file, City Clerk’s office), provided background information on the proposed development including its site context, design rationale, site plan, building elevations and façade treatments, proposed building materials and floor plans, highlighting the following:

 

§   

three-storey townhouse units are proposed along Williams Road and two-storey townhouses units are sited at the rear of the site in response to neighbouring single-family homes along the south side;

 

§   

proposed vehicle access is from Williams Road and there will be future connections of the proposed east-west internal drive aisle on the subject site to neighbouring properties to the east should these redevelop into a townhouse development in the future; and

 

§   

the existing public walkway along the west property line will be improved and widened and will provide pedestrian access to townhouse units along the west side as well as to the proposed common outdoor amenity area.

 

Donald Duncan, Donald Duncan Development Consultant Landscape Architect, provided an overview of the main landscape features of the project, noting that (i) the common outdoor amenity area is envisioned as a community gathering space, (ii) individual entrances to the townhouse units fronting the public walkway along the west property line will be gated, (iii) the size of trees proposed to be planted is appropriate for the size of the proposed development, and (iv) permeable paving treatment is proposed on portions of the internal drive aisles, including along the internal pedestrian walkways to enhance pedestrian safety.


 

Panel Discussion

 

In reply to queries from the Panel, Mr. Law and Mr. Duncan noted that (i) pedestrian access to the common outdoor amenity area from the public walkway will be gated, and (ii) appropriate measures including installation of barriers will be undertaken in order to protect the retained trees during construction.  

 

In reply to a query from the Panel, Wayne Craig, Director, Development, acknowledged that lighting along the public walkway will be provided through the Servicing Agreement for the proposed development.


 

Staff Comments 

 

Mr. Craig noted that (i) the three affordable housing rental units will be subject to a Housing Agreement to ensure tenant eligibility is consistent with the City’s Affordable Housing Strategy, (ii) the proposed development includes two convertible units, and (iii) a Servicing Agreement is associated with the project for site servicing and frontage works along Williams Road and improvements to the public walkway along the western edge of the subject site.

 

Mr. Craig further noted that revised Development Permit Considerations (attached to and forming part of these Minutes as Schedule 1) were distributed on table for Panel which clarify the agreement on driveway cross access to the future development to the east of the subject site and include the provision of wayfinding signage as part of the agreement. 

 

In reply to queries from the Panel, Mr. Craig clarified that (i) signage will be installed at the driveway entry of the subject site which include the address of the future development to the east, (ii) a left turn signage to the future development will be installed at the intersection of the driveway and the east-west internal drive aisle, (iii) the signages will not be installed until the future development occurs, and (iv)  signage will be installed at the terminus of the east-west internal drive aisle of the subject site indicating that future access to the east will be provided.


 

Gallery Comments

 

None.


 

Correspondence

 

Earl Luk and Quennie Law, 10031 No.4 Road (Schedule 2)

 

King Luk, 9840 Williams Road (Schedule 3)

 

Mr. Craig noted that (i) the above pieces of correspondence include, among others, a request for shared driveway access through the subject site for the future development to the east including installation of wayfinding signage, (ii) shared driveway access and installation of wayfinding signage on the subject site have been secured in an agreement, and (iii) staff has provided a written response to these correspondence.


 

Panel Discussion

 

The Panel expressed support for the project and appreciated the provision of three affordable low-end-market-rental (LEMR) units.


 

Panel Decision

 

It was moved and seconded

 

That a Development Permit be issued which would permit the construction of 18 townhouses, including three affordable housing units, at 9700, 9720 and 9800 Williams Road on a site zoned “Town Housing (ZT81) - Williams Road”.

 

CARRIED


2.

DEVELOPMENT PERMIT 17-794169   
(REDMS No. 6575604)

 

APPLICANT:

Yuanheng Seaview Developments Ltd. and Yuanheng Seaside Developments Ltd.

 

 

PROPERTY LOCATION:

3311 No. 3 Road and 3399 Corvette Way

 


 

INTENT OF PERMIT:

 

1.

Permit the construction of a high-rise mixed use development, including two residential towers containing 275 dwellings (with 22 affordable housing units), an office tower, street-oriented commercial uses, and a new City-owned community centre, at 3311 No. 3 Road; and

 

2.

Permit the construction of a high-rise multiple-family development, including two residential towers containing 89 dwellings, at 3399 Corvette Way;

 

on lands zoned “Residential/Limited Commercial and Community Amenity (ZMU30) – Capstan Village (City Centre)”.


 

Applicant’s Comments

 

Wing Leung, W.T. Leung Architects, with the aid of a PDF and video presentation (copy on file, City Clerk’s office), provided background information on Phase 2 (Lot B) and Phase 3 (Lot C) of the three-phase Viewstar development, including among others, their site context, site plan, architectural form and character, building elevations and façade treatments, highlighting the following:

 

§   

Lot B includes two residential towers, commercial uses including an office tower, a City-owned community centre, a public plaza at the southeast corner and a pocket park at the southwest corner of the subject lot;

 

§   

the entrance to the parking garage (two levels below grade and three levels above grade) including loading for Lot B is located off McMyn Way and the parking garage  is wrapped by the surrounding buildings;

 

§   

the curved façade of the office tower is anchored at the prominent No. 3 Road and Sea Island Way corner;

 

§   

an articulated perforated metal screen provides visual interest and screening for the above-ground parking garage along Sea Island Way;

 

§   

 

 

§   

there will be public art opportunities for the public plaza at the corner of No. 3 Road and McMyn Way as well as potentially on the façade of the community centre;

 

§   

curvilinear balconies with picket guards are proposed for the residential towers to provide visual interest and sun screening; 

 

§   

triple glazing is proposed for all buildings in Lot B and Lot C;

 

§   

Lot B buildings have been designed to achieve Step 3 of the BC Energy Step Code;

 

§   

Lot C (Phase 3) includes two triangular-shaped residential towers linked by a skybridge containing a swimming pool;

 

§   

vehicle entrance to underground parking for Lot C is through an autocourt off Corvette Way;

 

§   

public access to the dike is provided at the north and south ends of Lot C; 

 

§   

the landscaped River Road Park Entrance Plaza at the north end of Lot C provides public access and connects to the raised dike through stairs and ramps; and

 

§   

the Phase 3 (Lot C)  site will achieve Step 2 of the BC Energy Step Code.  A low carbon energy plant for the builing will be provided in accordance with City policy.

 

Daryl Tyacke, ETA Landscape Architects, provided an overview of the main landscape features of Lot B, noting that (i) proposed landscaping at the corner of No. 3 Road and Sea Island Way includes large planting beds, seating areas and rectangular paving patterns representing an aerial view of agricultural plots in Richmond, (ii) a community centre plaza is located at the corner of No. 3 Road and McMyn Way for public events, (iii) seating areas and planting are proposed at the pocket plaza at the corner of McMyn Way and Corvette Way, (iv) structural soil is proposed for off-site tree planting around the edge of the subject site to provide adequate soil volume,  and (v) landscaped multi-use outdoor amenity spaces for the residential and office towers are proposed on the podium roof level.

 

In addition, Mr. Tyacke briefed the Panel on the main landscape features of Lot C, noting that (i) stepped planter with seating and hedge planting provide screening to the south wall of the south building, (ii) hard and soft landscaping are proposed for the autocourt, (iii) an outdoor amenity area is proposed on Lot C podium that connects the two residential towers, and (iv) a green roof is proposed above the swimming pool.


 

Panel Discussion

 

In reply to queries from the Panel, Mr. Leung and Mr. Tyacke noted that (i) proposed lighting in landscaped areas in Lot B include bollard and step lights and strip LED lighting which will not create light pollution, (ii) the two parking entrances for Lot A (Phase 1) are located off McMyn Way and Corvette Way, and (iii) the proposed landscaping and lighting for the weather protected plaza at the north end of Lot C will encourage the public to use the access to the riverfront park.

 

In reply to a query from the Panel, Mr. Craig confirmed that Lot B contains 22 affordable low-end-market-rental (LEMR) units.  The developer oversupplied the affordable housing units provided in Phase 1 (Lot A) to devilver the units sooner andthe overall Viewstar development meets the City’s affordable housing requirements.


 

Staff Comments 

 

Mr. Craig noted that (i) buildings in Lot B and Lot C have been designed to comply with the City’s Aircraft Noise Policy, (ii) acoustical measures will be incorporated to achieve Canada Mortgage and Housing Corporation (CMHC) interior noise standards, (iii) there are significant Servicing Agreements associated with Lot B and Lot C for road improvements around the perimeter of the subject sites, dike upgrades and new waterfront park, and (iv) all proposed waterborne structures will not be part of the Servicing Agreement requirements as they will be constructed by the City with the developer providing a cash contribution as part of the rezoning process.

 

In reply to queries from the Panel, Mr. Craig confirmed that the entire riverfront park will be part of the Servicing Agreement and the developer will be responsible for the construction of all upland structures including the view structures.


 

Gallery Comments

 

David Dennis, 8191 River Road, queried about the start date of project construction and whether riparian development rights have been granted to the applicant. Also, he expressed concern regarding construction impacts on (i) land density of the east shoreline of the Fraser River, (ii) on-street parking along River Road, (iii) privacy of properties adjacent to the north end of Lot C, and (iv) water table of the shoreline construction.

 

With regard to the start date of construction and site preparation, Mr. Leung advised that (i) the applicant anticipates the issuance of Building Permit around the latter part of this year subject to completion of the application package, (ii) site preparation could occur after issuance of Building Permit, (iii) the water table of neighbouring sites will not be impacted during construction, and (iv) no pre-loading will be done for Lot C.

 

With regard to other construction concerns, Mr. Craig noted that (i) construction hours are regulated by the City’s Noise Bylaw, (ii) the applicant is required to provide a Construction Parking and Traffic Management Plan as part of the Building Permit process, and (iii) all construction within the dike and riverfront park will be subject to required environmental approvals.

 

With regard to concerns on privacy, Mr. Tyacke noted that the wall with guardrail on top at the north end of the dike will provide privacy and security to adjacent properties. In addition, Mr. Craig acknowledged that the project complies with the City’s tower separation requirements.


 

Correspondence

 

Radim Andrejevic, (no address provided) (Schedule 4)

 

Mr. Craig noted that Mr. Andrejevic expressed concerns related to project density, traffic congestion, and delayed delivery of the proposed community centre. In reply to project density and traffic concerns, Mr. Craig further noted that project density is outside of the purview of the Panel and the proposed significant road improvements around the subject sites would improve transportation in the neighbourhood.

 

With regard to Mr. Andrejevic’s concerns regarding the delivery of the proposed community centre, Mr. Craig advised that the delivery date for the community centre is established through the site rezoning and was revised by Council last year.


 

Panel Discussion

 

The Panel expressed support for the project, noting that (i) the project is well thought out and consistent with the rezoning application for the project, and (ii) the proposed public realm is well designed. Also, the Panel expressed appreciation for the presentation of the project and the provision of a community centre.


 

Panel Decision

 

It was moved and seconded

 

That a Development Permit be issued which would permit the construction of a:

 

1.

High-rise mixed use development, including two residential towers containing 275 dwellings (with 22 affordable housing units), an office tower, street-oriented commercial uses, and a new City-owned community centre, at 3311 No. 3 Road; and

 

2.

High-rise multiple-family development, including two residential towers containing 89 dwellings, at 3399 Corvette Way;

 

on lands zoned “Residential/Limited Commercial and Community Amenity (ZMU30) – Capstan Village (City Centre)”.

 

CARRIED


3.

DEVELOPMENT PERMIT 18-828900   
(REDMS No. 6211262)

 

APPLICANT:

1082009 BC Ltd.

 

 

PROPERTY LOCATION:

10760, 10780 Bridgeport Road and 3033, 3091, 3111 Shell Road

 


 

INTENT OF PERMIT:

 

1.

Permit the construction of 19 townhouse units at 10760, 10780 Bridgeport Road and 3033, 3091, 3111 Shell Road with vehicle access from Shell Road on a site zoned “Medium Density Townhouses (RTM3)”; and

 

2.

Vary the provisions of Richmond Zoning Bylaw 8500 to reduce:

 

 

(a)

the minimum lot width on major arterial road from 50.0 m to 43.3 m;

 

 

(b)

the minimum front yard setback to Bridgeport Road from 6.0 m to 3.3 m; and

 

 

(c)

the minimum exterior side yard setback to Shell Road from 6.0 m to 4.5 m.


 

Applicant’s Comments

 

Eric Law, Eric Law Architect, with the aid of a visual presentation (copy on file, City Clerk’s office), provided background information on the proposed development, including among others, its site context, site plan, architectural form and character, building elevations, floor plans, façade treatments, and building materials, highlighting the following:

 

§   

the contemporary design of the proposed townhouse development is in response to existing industrial developments across Shell Road;

 

§   

vehicular access to the site is from Shell Road;

 

§   

three-storey townhouse units in three clusters units and one building block consisting of two-storey townhouse units are proposed;

 

§   

the proposed building setback along Bridgeport Road will align with the building setback for the existing adjacent townhouse development to the west;

 

§   

a north-south private walkway is proposed along the west property line to provide pedestrian access to units in the townhouse building fronting onto the walkway;

 

§   

the proposed common outdoor amenity area is centrally located;

 

§   

two secondary suites are proposed; and

 

§   

the existing mature trees along the south property line will be retained and protected.

 

Donald Duncan, Donald Duncan Development Consultant Landscape Architect, provided an overview of the main landscape features of the project, noting that (i) the hammerhead area also serves as a public plaza space and complements the proposed common outdoor amenity area, (ii) permeable paving treatment is proposed for the private pedestrian walkway, and (iii) substantial planting is proposed at the north end of the internal drive aisle to screen headlight glare.

 

In reply to a query from the Panel, Mr. Duncan noted that existing mature trees to be retained along the south property line will be protected during construction.


 

Staff Comments

 

Mr. Craig noted that (i) the three proposed variances associated with the project were identified at the rezoning stage and no concerns from the public were noted, (ii) the proposed setback variances are a function of significant road dedication required along Shell Road and Bridgeport Road, and (iii) an acoustical report has been provided by the applicant which confirmed that the proposed development will achieve CMHC interior noise standards.


 

Gallery Comments

 

None.


 

Correspondence

 

None.


 

Panel Decision

 

It was moved and seconded

 

That a Development Permit be issued which would:

 

1.

permit the construction of 19 townhouse units at 10760, 10780 Bridgeport Road and 3033, 3091, 3111 Shell Road with vehicle access from Shell Road on a site zoned “Medium Density Townhouses (RTM3)”; and

 

2.

vary the provisions of Richmond Zoning Bylaw 8500 to reduce:

 

 

(a)

the minimum lot width on major arterial road from 50.0 m to 43.3 m;

 

 

(b)

the minimum front yard setback to Bridgeport Road from 6.0 m to 3.3 m; and

 

 

(c)

the minimum exterior side yard setback to Shell Road from 6.0 m to 4.5 m.

 

CARRIED


4.

Date of Next Meeting:    April 26, 2021


5.

Adjournment


 

It was moved and seconded

 

That the meeting be adjourned at 5:25 p.m.

 

CARRIED


 

Certified a true and correct copy of the Minutes of the meeting of the Development Permit Panel of the Council of the City of Richmond held on Wednesday, April 14, 2021.

_______________________________

_____________________________

Joe Erceg 
Chair

Rustico Agawin 
Committee Clerk