July 2, 2024 - Agenda
General Purposes Committee
Electronic Meeting
Anderson Room, City Hall
6911 No. 3 Road
Tuesday, July 2, 2024
4:00 p.m.
Pg. # |
ITEM |
|
|
|
MINUTES |
GP-4 |
|
Motion to adopt the minutes of the meeting of the General Purposes Committee held on June 17, 2024. |
||
|
|
|
||
|
|
PRESENTATION |
|
1. |
Yannick Simovich, Board Chair, Tourism Richmond, and Nancy Small, CEO, Tourism Richmond, to provide an update on the tourism sector in Richmond and Tourism Richmond’s plans and initiatives. |
|
|
FINANCE AND CORPORATE SERVICES DIVISION |
|
2. |
DEVELOPMENT OF A RICHMOND TOURISM MASTER PLAN (File Ref. No. 08-4150-01) (REDMS No. 7706191) |
||
GP-12 |
|
See Page GP-12 for full report |
||
|
|
Designated Speaker: Jill Shirey and Katie Ferland |
||
|
|
STAFF RECOMMENDATION |
||
|
|
That the approach to developing a Richmond Tourism Master Plan, including the guiding principles, as outlined in the staff report titled, “Development of a Richmond Tourism Master Plan,” dated June 10, 2024, from the Director, Business Services, be endorsed. |
||
|
|
|
||
|
|
DEPUTY CAO’S OFFICE |
|
3. |
HUGH BOYD COMMUNITY FACILITY AND FIELDHOUSE – PROGRAM, SITE SELECTION, FORM AND CONCEPT DESIGN |
|||
GP-17 |
|
See Page GP-17 for full report |
|||
|
|
Designated Speaker: Martin Younis and Keith Miller |
|||
|
|
STAFF RECOMMENDATIONS |
|||
|
|
(1) |
That the program, Site A location, two-storey form and concept design as described in the staff report titled, “Hugh Boyd Community Facility and Fieldhouse – Program, Site Selection, Form and Concept Design,” dated June 3, 2024, from the Director, Facilities and Project Development and the Director, Recreation and Sport Services, be approved; |
||
|
|
(2) |
That the existing small fieldhouse be demolished as outlined in the report titled, “Hugh Boyd Community Facility and Fieldhouse – Program, Site Selection, Form and Concept Design,” dated June 3, 2024, from the Director, Facilities and Project Development and the Director, Recreation and Sport Services; |
||
|
|
(3) |
That the capital budget in the amount of $19 million be approved and funded from the Growing Communities Reserve Fund ($17,712,669) and Capital Building and Infrastructure Reserve ($1,287,331) as outlined in the report titled, “Hugh Boyd Community Facility and Fieldhouse – Program, Site Selection, Form and Concept Design,” dated June 3, 2024, from the Director, Facilities and Project Development and the Director, Recreation and Sport Services; and |
||
|
|
(4) |
That the Consolidated 5 year Financial Plan (2024-2028) be amended accordingly. |
||
|
|
|
|||
|
|
ADJOURNMENT |
||
|
|
|
||